Week of May 8th-12th

Installed french drain, backfilled sub-grade in preparation for the interior slab. Plumbing sub-rough installed. Plumbing sub-rough inspection completed.

Week of May 15th-19th

Installed rebar mat and insulated for radiant heat tube. Radiant heat tube installed and inspected. Poured basement slab.

Week of May 22nd-26th
Set steel columns and beams. Framing basement walls.

Week of May 29th-June 2nd
Set main level iron floor beams. Framing lower level. Backfilling foundation walls and hauling off excess materials.